The Latest on Paul First Nation Solar Project

 In Solar

Recent Milestones
Completed a wetlands analysis to identify and preserve the most sensitive wetland
Held 4 information sessions with the Paul First Nation community
Modified the lay-out design of the solar panels preserve the most ecologically sensitive wetlands
Successfully passed the business case stage, proving the Project’s economic viability
Latest: Successfully passed Gate 2 in the Alberta Energy System Operator connection queue

Next Steps
Prepare the Project for the next stage: Permitting, Contracting and Financing
Confirm the interconnect (ability to connect the plant into the power grid)
Conduct a wildlife study
Prepare and submit a Detailed Environmental Review Report to Indigenous Services Canada
Finalize Project partners and financing